AKU Diathermic Oil Evaporator

Project Specifications

  • Type: Indirect diathermic oil evaporator
  • Client: Confidential
  • Dimensions: approximately 2 x 4 x 2.5 m
  • Regulatory Compliance: PED Directive, Category IV
  • Services Provided: Thermal calculation, operational logic design, engineering design, fabrication, insulation, workshop testing, on-site installation
  • Logistics Solution: Skid pre-assembled and pre-wired in the workshop for transport via standard vehicles
  • Installation Location: Province of Cuneo, Italy

Indirect Evaporator

The project began with the feasibility study provided by the client, from which the input data for the equipment’s thermal calculations were derived. After defining the geometry, we proceeded to the detailed design phase (calculation of wall thicknesses and 3D as-built modeling). At the same time, we developed the machine’s operational diagram (P&ID), coordinating the software design and the selection of components necessary for commissioning (selection of instruments and components, identification of suppliers, and coordination with the quality department and the welding coordinator regarding material selection).

The plant, as a whole, incorporates a pressure vessel for steam production, two distribution manifolds for the primary and secondary fluids, supports, and piping for connection to the existing plant.

Off-Site Prefabrication

The key to meeting the project’s constraints was the off-site prefabrication of the entire system.

The on-site installation phase required the end client to coordinate numerous parties (mechanical installer—MM Construction—electrical installer, software engineers, insulation installers, and production site personnel for the switchover between the old and new systems). For this reason, a solution was chosen that involved prefabricating the entire system in the workshop, using a 3D scan of the building and the existing system to enable the detailed design and 3D modeling of the new system.

On-site Installation and Start-up

This phase involved on-site installation directly supervised by MM Construction personnel, both during the unloading and positioning of the main components and during the dismantling of the system to be revamped and the installation of the new one.

The final steps involved MM Construction personnel assisting the client during the start-up and commissioning phase, in the presence of the notified body responsible for verifying proper operation.

 